Client: South Eastern Education & Library Board, Grahamsbridge Road, Dundonald, Belfast (Phase 3)

Project/Contract: Phase 3 - Childrens Playground.
NEC form contract
Description: New sensory garden and playground for children
with learning difficulties and disabilities including
paths, drainage and landscaping.
Value: £100,000.00
Construction Period: 12 Weeks
Status: On site
Architect: co SEELB
Client: St Marys University College, Belfast

Project/Contract: Replacement Curtain Walling, Roofs and Internal Alterations
Description: Replacement of all external windows/curtain walling with new
Metal Technology Aluminium Windows, Doors and Curtain
Walling Systems. Concrete repairs to areas.
General refurbishments including internal room upgrades.
Extensive flat roof repairs and new rooflights.
DDA upgrade works incl new external ramps, handrails etc.
Value: £515,000.00
Construction Period: 16 Weeks
Status: Completed Early
Architect: FCM Partnership,
431-441 Newtownards Road,
Belfast,
BT4 1AQ.
Contact: Damian Murphy,
T/N: 9045 5188
Client: Ballymacormick Road, Bangor

Project/Contract: Ballymacormick Road, Bangor.
Reverty - Chris Collins - 07714 100625
Description: 2 new build residential dwellings to turnkey high quality
finish. Traditional style with block and k rend, tiled
roofs, pvc windows, services and all finishes. Extensive external works and landscaping.
Value: £200,000
Construction Period: 26 Weeks
Status: On site
Architect: Dimensions,
Montgomery House,
478 Castlereagh Road,
Belfast,
BT5 6BQ.
Contact: Jim Armstrong - 90705965
Client: Scolie Na Fuiseoige,
Summerhill Road, Twinbrook, Belfast

Project/Contract: New extension and upgrade to toilets/kitchen,
JCT Intermediate Form
Description: Alterations and Refurbishment Works to include;
new extension to create toilets and additional rooms,
internal upgrade to toilets/kitchens with all associated
finishes/services. External works including new store. In live school environment under stringent conditions.
Value: £75,000
Construction Period: 10 Weeks
Status: Completed Early
Architect: Povall Worthington,
5 Pilots View,
Heron Road,
Belfast,
BT3 9JE.
Gary McCone,
T/N 90450105
Client: Osborne Park, Belfast

Project/Contract: New Car Park / Childrens Playgrounds
Description: Alterations and Extensions to Existing Dwelling.
To create complete new upgraded house in keeping with
the areas strict planning constraints. Extensive external works and landscaping.
Value: £400,000
Construction Period: 20 Weeks
Status: On site
Architect: Jan Madill,
80 Purdysburn Hill,
Belfast,
BT8 8JZ.
Contact: Jan Madill - 07703 360531
|