Client: South Eastern Education & Library Board, Grahamsbridge Road, Dundonald, Belfast (Phase 3)






Project/Contract:
Phase 3 - Childrens Playground. NEC form contract

Description: New sensory garden and playground for children with learning difficulties and disabilities including paths, drainage and landscaping.

Value: £100,000.00

Construction Period: 12 Weeks

Status: On site

Architect: co SEELB



Client: St Marys University College, Belfast




Project/Contract:
Replacement Curtain Walling, Roofs and Internal Alterations

Description: Replacement of all external windows/curtain walling with new Metal Technology Aluminium Windows, Doors and Curtain Walling Systems. Concrete repairs to areas. General refurbishments including internal room upgrades. Extensive flat roof repairs and new rooflights.
DDA upgrade works incl new external ramps, handrails etc.

Value: £515,000.00

Construction Period: 16 Weeks

Status: Completed Early

Architect: FCM Partnership, 431-441 Newtownards Road, Belfast, BT4 1AQ. Contact: Damian Murphy, T/N: 9045 5188


Client: Ballymacormick Road, Bangor





Project/Contract:
Ballymacormick Road, Bangor. Reverty - Chris Collins - 07714 100625

Description: 2 new build residential dwellings to turnkey high quality finish. Traditional style with block and k rend, tiled roofs, pvc windows, services and all finishes. Extensive external works and landscaping.

Value: £200,000

Construction Period: 26 Weeks

Status: On site

Architect: Dimensions, Montgomery House, 478 Castlereagh Road, Belfast, BT5 6BQ. Contact: Jim Armstrong - 90705965



Client: Scolie Na Fuiseoige, Summerhill Road, Twinbrook, Belfast





Project/Contract:
New extension and upgrade to toilets/kitchen, JCT Intermediate Form

Description: Alterations and Refurbishment Works to include; new extension to create toilets and additional rooms, internal upgrade to toilets/kitchens with all associated finishes/services. External works including new store. In live school environment under stringent conditions.

Value: £75,000

Construction Period: 10 Weeks

Status: Completed Early

Architect: Povall Worthington, 5 Pilots View, Heron Road, Belfast, BT3 9JE. Gary McCone, T/N 90450105


Client: Osborne Park, Belfast




Project/Contract:
New Car Park / Childrens Playgrounds

Description: Alterations and Extensions to Existing Dwelling. To create complete new upgraded house in keeping with the areas strict planning constraints. Extensive external works and landscaping.

Value: £400,000

Construction Period: 20 Weeks

Status: On site

Architect: Jan Madill, 80 Purdysburn Hill, Belfast, BT8 8JZ. Contact: Jan Madill - 07703 360531


 