Bavan Contracts
 
 

 

Client: St Marys University College, Belfast

St Marys University College, Belfast


Project/Contract:
Student Union Refurbishment

Description: Complete refurbishment of the old students union to include all alterations, wall, floor and ceiling finishes. Relocation of cafe facilities and new built in furniture. Upgrade of electrical and mechanical services.

Value: £100,000.00

Construction Period: 8 Weeks - February - April 2011 Practical Completion

Status: Completed on time

Architect: TODD ARCHITECTS, 41-43 Hill Street, Belfast, BT1 2PB. Contact: Peter Logan, T/N: 9024 5587


Client: The Salvation Army

The Salvation Army

Project/Contract:
Replacement Roof and Internal Alterations.

Description: The works comprised of replacement roof covering, replacement windows and doors, upgrading fire resistance of the building. Mechanical and Electrical services upgrades and alterations to meet current standards. Internal and external redecorations. DDA upgrade works incl new external ramps, handrails etc.

Value: £125,000.00

Construction Period: 12 Weeks - June - August 2011

Status: Completed on time and budget

Architect: FCM Partnership, 431-441 Newtownards Road, Belfast, BT4 1AQ. Contact: Damian Murphy, T/N: 9045 5188


Client: Finnard Rural Development Association

Finnard Rural Development Association

Project/Contract:
New extension and general refurbishment of existing buildings including extensive siteworks/drainage.

Description: Extension / General fit out works to include; new kitchen, and bathrooms. Traditional block / pitched roof construction with sundry works to exisiting hall including all mechanical and electrical works. Drainage and siteworks incl DDA works.

Value: £75,000.00

Construction Period: 16 Weeks - Jan - May 2011

Status: Completed early and under budget

Architect: Marcus Bingham, 9 Tullyquilly Road, Rathfriland. Contact: Marcus Bingham, T/N: 4063 8842


Client: Our Lady & St Patricks P S Trustees, Edward St, Downpatrick BT30 6JD

Our Lady & St Patricks P S Trustees, Edward St, Downpatrick

Project/Contract:
Alteration Works to facilitate Amalgamation. NEC Form Contract

Description: Alterations and Refurbishment Works to include;upgrade to all rooms incl all finishes, new toilet facilities, internal alterations to corridors/rooms. Extensive upgrade to services incl new boilers, emergency lighting/fire alarms/controls. New car parking areas and associated drainage/landscaping. In live school environment under stringent conditions.

Value: £350,000.00

Construction Period: 12 Weeks - June - August 2011 Practical Completion

Status: Completed on time and budget.

Architect: Isherwood & Ellis, 15 Malone Road, Belfast, BT9 6RJ. T/N 90663291 - Richard Lennox.


Client: Rathmore Grammar School, Belfast

Rathmore Grammar School, Belfast

Project/Contract:
Toilet Refurbishment / MRI Room upgrade

Description: Complete refurbishment of staff toilets / MRI Room to include all alterations, wall, floor and ceiling finishes. New Fitted Furniture/Cubicles/IPS Panels. Upgrade of electrical and mechanical services.

Value: £50,000.00

Construction Period: 4 Weeks - August 2011 Practical Completion

Status: Completed on time and budget.

Architect: Bureau 39, 38 Oakland Avenue, Belfast, BT4 3BW. Contact: Peter Logan, T/N: 07527323639.


Client: Osborne Park, Belfast

Osborne Park, Belfast

Project/Contract:
Osborne Park, Belfast. Mr Gerry Mallon - 07880 715830

Description: Alterations and Extensions to Existing Dwelling.To create complete new upgraded house in keeping with the areas strict planning constraints. Extensive external works and landscaping.

Value: £450,000.00

Construction Period: 24 Weeks

Status: Completed on time.

Architect: Jan Madill, 80 Purdysburn Hill, Belfast, BT8 8JZ. Contact: Jan Madill - 07703 360531



Client: South Eastern Education & Library Board, Grahamsbridge Road, Dundonald, Belfast (Phase 3)


South Eastern Education & Library Board, Grahamsbridge Road, Dundonald, Belfast (Phase 3)

Project/Contract:
Phase 3 - Childrens Playground. NEC form contract

Description: New sensory garden and playground for children with learning difficulties and disabilities including paths, drainage and landscaping.

Value: £100,000.00

Construction Period: 12 Weeks

Status: Completed Early and under budget

Architect: Co SEELB


Client: Sunnybank Garden Centre


Sunnybank Garden Centre

Project/Contract:
New Warehouse Unit / Offices

Description: New warehouse unit to include;New portal steel framed building with cladding services, extensive internal fit out/new offices Site works to include reinforced retaining walls and ramps, carpark, pallisade fencing etc

Value: £375,000.00

Construction Period: 25 Weeks

Status: Completed Early

Architect: East Antrim Architectural, 23 Fountain Street, Antrim, BT41 4BG. Contact: Roy Seaton. Tel: 9442 9079



Client: Board of Governors at CBSS, Glen Road, Belfast


Board of Governors at CBSS, Glen Road, Belfast

Project/Contract:
Upgrade to Home Economics suite and creation new facilities. General refurbishment to existing stores and classrooms, associated with upgrade.

Description: Complete refurbishment of existing facilities in live school environment to suit clients needs. New openings created coupled with all finishes, mechanical and electrical works to create new high specification facilities for pupils of various ages and needs in live school. Careful planning was adopted to enable useage of facilities and works outside hours required to facilitate clients needs and to achieve the stringent programme.

Value: £100,000.00

Construction Period: 8 Weeks

Status: Completed Early

Architect: Bernard Mc Guinness, 319 Cavehill Road, Belfast, BT15 5EY. TEL - 90 900 558


Client: Qualitrol Hathaway Limited , Belfast


Qualitrol Hathaway Limited , Belfast

Project/Contract:
Conversion of existing buildings into Production Area, New Toilets, Canteen Facilities and External Works, JCT Intermediate Form

Description: Extension / General fit out works to include; new facilities, and high specification clean rooms/production areas. All fast track fit out to live facility to enhance current building. Works consist all alterations, finishes and mechanical / electrical works.

Value: £275,000.00

Construction Period: 16 Weeks

Status: Completed Early

Architect: Blamphin & Associates, 80 Malone Avenue, Belfast. Contact: Paul Blamphin, T/N: 9066 7918


Client: O'Kane Food Service, Lisburn


O'Kane Food Service, Lisburn

Project/Contract:
Construction of 5 new Loading Bays, Refurbishment of Existing Cold Store Warehouse

Description: Open up existing gables and erect new steel frame cladding etc. Form dock levellers including new pits Refurbishment and alteration of existing cold storage warehouse including all new panels and services works required whilst still in live operation Extensive site works - new car parking, floodlighting and landscaping including associated drainage.

Value: £200,000.00

Construction Period: 3 months phased construction

Status: Completed Early

Architect: Blamphin & Associates, 80 Malone Avenue, Belfast. Contact: Paul Blamphin, T/N: 9066 7918


Client: Castlereagh Borough Council


Castlereagh Borough Council

Project/Contract:
Lough Moss Leisure Centre

Description: Refurbishment of 2 squash courts including all specialist fittings and finishings to areas. New Mechanical and Electrical Services throughout all done whilst centre is live.

Value: £50,000.00

Construction Period: 8 Weeks

Status: Completed Early

Architect: C/O Castlereagh Borough Council


 

Client: South Eastern Education & Library Board


Harmony Hill PS

Project/Contract:
Internal & External DDA Improvement Works

Description: Alterations and Refurbishment Works to include; new ramps, lift installations, foundations, steelwork, curtain walling, roof cladding, new toilet facilities, floor finishes, hard and soft landscaping.

Value: £260,000.00

Construction Period: 9 Weeks

Status: Recently completed within time and budget - awaiting reference

Architect: Andrew Nesbitt Architects, Carnagie Studio, Liblary Hill, 121 Donegall Road, Belfast BT12 5JL



Client: O'Kane Food Service, 221 Hillhall Road, Lisburn

O'Kane Food Service

Project/Contract: Construction of Loading Bays & Ramps to Warehouse. Refurbishment of Existing Warehouses & Offices

Description: Cordon off existing factory cold rooms and hygiene rooms with temporary partitions. Open up existing gables anderect new structural steel frame. External cladding, internal cold rooms. Form dock levellers. Refurbishment and alteration of existing offices. Form external ramps in reinforced concrete. Survey existing drainage system and install new. Extensive site works and landscaping.

Value: £650,000.00

Construction Period: 5 months phased construction

Status: Phase 1 complete

Architect: Blamphin & Associates, 80 Malone Avenue, Belfast. Contact: Paul Blamphin.


Client: A, S & D Enterprises, C/O McConnell Martin, Metropole House, Donegal Street, Belfast

Sinclair House

Project/Contract: Refurbishment of Sinclair House

Description: Refurbishment of external façade to listed building including flat roof repairs.

Value: £150,000.00

Construction Period: 12 Weeks

Status: Completed early

Architect: Blamphin & Associates, 80 Malone Avenue, Belfast. Contact: Paul Blamphin.


Client: Castlereagh Borough Council

Project/Contract: Moneyreagh Community Centre

Description: Construction of new community centre, works to include; Piled foundations, precast concrete floors, facing block and decorative render, aluminium windows and doors, metal railings and balcony's, sports hall floors, decorations and siteworks.

Value: £75,000.00

Construction Period: 40 Weeks

Status: completed December 2008 ahead programme

Architect: Anderson Williamson Ltd, Building 9, Citylink Business Park, Durham Street, Belfast.


Client: South Eastern Health & Social Care Trust




Project/Contract:
Ulster Hospital - Kitchen Refurbishments

Description: Refurbishment Works to 27 no kitchens including all alterations, new kitchens, finishes, all services to live environment

Value: £150,000.00

Construction Period: 8 Weeks

Status: Commened March 2009

Architect: Hamilton Architects, 163 Upper Newtownards Road, Belfast, BT4 3HZ. Contact: Richard Keys, T/N: 9065 6262


Client: South Eastern Health & Social Care Trust




Project/Contract:
Lagan Valley Hospital - New Conference Room/Library

Description: Refurbishment Works to create new conference room and Library incl all alterations / finishes / services etc

Value: £65,000.00

Construction Period: 8 Weeks

Status: Commenced March 2009

Architect: Hamilton Architects, 163 Upper Newtownards Road, Belfast, BT4 3HZ. Contact: Richard Keys, T/N: 9065 6262


Client: Illusion Properties


Orchard Way Business Park

Project/Contract:
New Business Units, Phase 1 (On Hold), Orchard Way, Antrim

Description: Large Civil Works and Construction of 30 new 2 storey business units

Value: £4,500,000.00

Construction Period: 52 Weeks

Status: Completed phase 1 July 2008

Architect: Bryson Architects, Lynden Gate, 50 Knockbreda Road, Belfast BT6 0JB



Client: Belfast Health & Social Care Trust, Belfast City Hospital


Belfast City Hospital

Project/Contract:
Refurbishment & Alterations to BCH Transport Dept

Description: Alterations and Refurbishment Works to include; stripping out and reinstatement work to former BCH Laundry (retained portion). Site works to include reinforced retaining walls and ramps, carpark, pallisade fencing, car wash facilities.

Value: £200,000.00

Construction Period: 10 Weeks

Status: Completed March 2009 ahead of programme and under budget

Architect: JCP Consulting, Lomond House, 85-87 Holywood Road, Belfast, BT4 3BD. Contact: Arden Pollock



Client: Parish of St. Comgall's Church, Donaghadee


St. Comgall's Church

Project/Contract:
Refurbishment Works to existing Church

Description: Gutting out of existing building, including removal of entrance porch and internal walls, removal of asbestos and form new openings. New doors, frames and screens. Make good all defective plaster and render. All new plumbing, heating and electrics. Site works to include new paths, car parks and landscaping.

Value: £380,000.00

Construction Period: 10 Weeks

Status: Completed September 2007 ahead programme

Architect: WH Stephens, Stephens House, 63 Malone Road, Belfast, BT9 6SA


Quantity Surveyor: WH Stephens, Stephens House, 63 Malone Road, Belfast, BT9 6SA


Reference:

Bavan Contracts Limited were the main contractors on the above project. The project was completed on time and on budget with the highest possible standard of workmanship. The site manager was extremely competent and efficient and ensured all Health & Safety matters were attended to throughout the course of the works. The back up support and administration of the contract was excellent and we would have no hesitation in recommending this contractor for any future projects.

Yours Faithfully

W.H. STEPHENS


Client: Corpus Christi Youth Centre, Belfast Metropolitan College,
Whiterock Road, Belfast



Corpus Christi Youth Centre

Project/Contract:
General refurbishment of existing buildings

Description: General refurbishment to include; new technology room, new composite cladded roof and repairs to existing. Upgrade heating system and electrics, new windows and doors, plastering, structural repairs, new floor to sports hall with underfloor heating, floor finishes, decorations and site works.

Value: £250,000.00

Construction Period: 14 Weeks

Status: Completed

Architect: Paddy Byrne Architects, Twin Spires Centre, 155 Northumberland Street, Belfast, BT13 2JF


Client: South Eastern Health & Social Care Trust




Project/Contract:
Downshire Hospital - Accomodation Refurbishment

Description: Refurbishment Works to 8 no apartments including all alterations, new kitchens, finishes,bathrooms, services etc

Value: £180,000.00

Construction Period: 12 Weeks

Status: Commenced March 2009

Architect: Hamilton Architects, 163 Upper Newtownards Road, Belfast, BT4 3HZ. Contact: Richard Keys, T/N: 9065 6262




Client: Green Island House


Green Island House

Project/Contract:
Downview Park, Greenisland

Description: Alterations and Extensions to Existing Dwelling. Landscaping and Site Works

Value: £325,000.00

Construction Period: 20 Weeks

Status: completed December 2008 ahead of programme

Architect: Neil Mathews Architects, Building 5, Weaver's Court, Belfast, BT12 5GH. Contact Neil Matthews



Client: Richard & Kathy McMullan


Helen' Bay

Project/Contract:
Kathleen Ave, Helen's Bay

Description: Alterations and Extensions to Existing Dwelling. New Garage, Road Re-alignment & Landscaping

Value: £355,000.00

Construction Period: 20 Weeks

Status: completed December 2008

Architect: Blamphin & Associates, 80 Malone Avenue, Belfast. Contact: Paul Blamphin


Client: Artability Charity Ltd


Awaiting Image

Project/Contract:
Alterations and New Lift to Existing Offices for DDA

Description: Refurbishment Works to include; New access lift, new WC areas, doors, ramps, floor, wall and ceiling finishes and all services to meet current DDA compliant standards.

Value: £125,000.00

Construction Period: 8 Weeks

Status: Completed March 2009

Architect: Jackson Graham Architects, 14/16 Shore Road, Holywood, BT18 9HX. Contact: Jeremy Jackson, T/N: 9096 0999



Client: Northern Health & Social Care Trust


Clonmore Residental Home

Project/Contract:
Clonmore Residential Home

Description: Upgrading of fire rating to all doors, screens and ducts. Mechanical and Electrical works

Value: £45,000.00

Construction Period: 8 Weeks

Status: Completed February 2009

Architect: Estate Services Directorate, Holywood Hospital, 60 Steeple Road, Antrim, BT41 2RJ



Client: Board of Governors, St Joseph's Primary School


Saint Josephs

Project / Contract: Refurbishment Works to existing School

Description: Replacement of all external timber windows with new Metal Technology Aluminium Windows, Doors and Curtain Walling Systems. Replacement of internal timber fire screens. General refurbishments including concrete repairs.

Value: £280,000.00

Construction Period: 12 Weeks

Status: Completed 3 weeks early

Architect: WH Stephens, Stephens House, 63 Malone Road, Belfast, BT9 6SA, Contact: Darren Press
T/N: 9066 3123

Quantity Surveyor: WH Stephens, Stephens House, 63 Malone Road, Belfast BT9 6SA


Reference:



To Whom It May Concern

During the months of Januray, Februray and March of this year, Bavan Contracts carried out a major contract in St. Joseph's Primary School, replacing windows and skylights and improving the heating system throughout the building. Now that the work has been completed, I am very satisfied with the improvements undertaken, the standard of workmanship, the management of the same work and the quality of supervision.

The company worked very closely with the school during the time of the project and was sensitive to the routines of school life. Health and Safety issues were always paramount and addressed sensibly by the contractors with risk assessment an integral part of the project. I would be very happy in re-employing Bavan Contracts to undertake any future work at St. Joseph's Primary School.

JJ Ryan
Principal


Client: International House Belfast Limited



International House Belfast Limited

Project/Contract:
109 - 111 University Street, Belfast

Description: Refurbishment and conversion of existing building into a teaching facility.

Value: £250,000.00

Construction Period: 8 Weeks

Status: Completed March 2007

Client Consultant: Kearney Consulting Ltd.

Reference:

To whom it may concern

Bavan Contracts Limited were the main contractors on the above project. The project was completed on time and on budget with the highest possible standard of workmanship. The site manager was extremely competent and efficient and ensured all Health & Safety matters were attended to throughout the course of the works. The back up support and administration of the contract was excellent and we would
have no hestitation in recommending this contractor for any future projects.

Yours Faithfully

For: International House Belfast Ltd


Client: Franck Pelissou


Franck Pelissou

Project/Contract:
22 Chesnut Grove, Newry

Description: Alterations and extensions to dwelling and roof space conversion

Value: £190,000.00

Construction Period: 20 Weeks

Status: Completed

Architect: Cathal Grant, 45 Bavan Road, Mayobridge, Newry


Client: Board of Governors at St. Vincent De Paul Primary School,
Ligoniel Road, Belfast


SVP

Project / Contract: New toilets facilities, health and safety improvments, General refurbishment.

Description: Gutting out of existing rooms, forming new openings, re-fitting rooms. Mechanical and Electrical works.

Value: £160,000.00

Construction Period: 12 Weeks

Status: Completed 1 week early

Architect: James P Rooney, 783A Antrim Road, Newtownabbey, BT36 7PW
Contact: Jim Rooney T/N: 9028 9467

Quantity Surveyor: Wright & Partners, 637 Lisburn Road, Belfast BT9 7GT


Reference:



To Whom It May Concern

Bavan Contracts began extensive work to refurbish the children's tiolets throughout St Vincent de Paul Primary School in December 2007. The work was completed by the end of February to a very high standard and has greatly improved the school environment.

During the refurbishments the company worked very closely with the school to ensure that disruption to school routines was kept to a bare minimum. All of the staff employed by the contractors were diligent in their work and conducted themselves in a professional manner. Great attention was paid to health and sfaety issues with constant monitoring and review of work being undertaken to ensure the safety of everyone in the school was maintained at a high standard.

I would be very happy to re-employ Bavan Contracts for any future work in St Vincent de Paul and would have no objection in recommending them for other contracts within the eductaion sector.

Yours Sincerely

Mrs Margaret McLaughlin
Acting Principal


Client: St John's Ambulance, Saintfield Road, Belfast


St. John's Ambulance

Project / Contract: Fit Out and general refurbishment of existing buildings

Description: General fit out works to include; new training rooms, kitchen, toilets, offices, stores and reception. Fire proofing of party walls. Insulating external walls. New curtain walling and shop fronts. Mechanical and Electrical works. Drainage alterations.

Value:£95,000

Construction Period: 6 Weeks

Status: Completed on Programme

Architect: Blamphin & Associates, 80 Malone Avenue, Belfast Contact: Paul Blamphin T/N: 9066 7918


Reference:



To Whom It May Concern

Fit Out of Ambulance Station, Brackenvale, Belfast for St John Ambulance

Bavan Contracts Ltd were the Main Contractors for this project.

Bavan Contracts completed the works on time and budget to a good standard of finish.

We found them flexible and attentive in dealing with unforeseen circumstances and contract variations and would have no hestitation in recommending them for further contracts.

Yours Faithfully

Blamphin + Associates


Client: Newmount Credit Union


Newmount Credit Union

Project/Contract:
Extension to and refurb of existing building

Description: Extension to existing building, refurbishment of existing building and site works.

Value: £90,000.00

Construction Period: 10 Weeks

Status: completed December 2007 under budget

Architect: WH Stephens, Stephens House, 63 Malone Road, Belfast, BT9 6S


Client: Jack Connolly


Carlin Records

Project/Contract:
Carlin Record Store, Newry

Description: Refurbishment of existing building. Works include replacing existing roof whilst the building is occupied.

Value: £80,000.00

Construction Period: 8 Weeks

Status: Completed

Reference:


Bavan Contracts Limited were the main contractors on the above project. The project was completed on time and on budget with the highest possible standard of workmanship. Although it was a difficult site the works were managed extremely well. We were also happy with the Health & Safety measures taken throughout the course of the works.
We would have no hesitation in recommending this contractor for any future projects.

Yours Faithfully

Jack Connolly


Client: Board of Governors at Hazelwood IPS



Hazelwood School

Project/Contract:
New Hygiene Rooms Hazelwood IPS

Description: Gutting out of existing rooms, forming new openings, re-fitting rooms. mechanical and Electrical works.

Value: £50,000.00

Construction Period: 3 Weeks

Status: Completed

Architect: Paul Anderson Chartered Architect, 34 Woodfield, Jordanstown Road, Newtownabbey, Co. Antrim


Reference:

To whom it may concern

I have recently worked on the construction of a new Hygiene Room at Hazelwood Integrated Primary School with Bavan Contracts Ltd and I am able to say that high standards have been displayed and maintained and their ability to remain within programme is exemplary.
I would have no difficulty in recommending them for other works.

Yours Faithfully

Paul Anderson RIBA


Client: Board of Governors at St. Oliver Plunkets Primary School


St. Oliver Plunketts

Project/Contract:
New Toilet Facilities, health and safety improvements. General Refurbishment.

Description:
Gutting out of existing rooms, forming new openings, re-fitting rooms. mechanical and electrical works.

Value: £120,000.00

Construction Period: 8 Weeks

Status: Completed within time and budget

Architect: Donnelly O'Neill Architects, The Old Throne Hospital, 244 Whitewell Road, Newtownabbey, Co. Antrim BT36 7ES

Reference:

To Whom It May Concern:

Bavan Contracts were appointed for refurbishment work to existing toilets in St Oliver Plunkett Primary School Belfast. This work involved refurbishing the existing toilets in a sequenced programme during school term time. Bavan Contracts carried out the work in a professional manner and kept the school informed of progress throughout the course of the works.

We would include Bavan Contracts on future select lists.

Yours faithfully

Donnelly & O Neill Ltd BSc Dip Arch RIBA MRIAI
CHARTERED ARCHITECTS


Client: St Martin's Church, Newtownards Road, Belfast


Saint Martin's Church

Project/Contract:
General refurbishment and extension to existing buildings

Description: Structural alterations, forming new rooms, plastering, Mechanical and Electrical Works. Decorations and floor finishes within live church.

Value: £50,000.00

Construction Period: 4 Weeks

Status: Completed

Architect: Blamphin & Associates, 80 Malone Avenue, Belfast Contact: Paul Blamphin


Client: St Mary's Church, Dusford, Ardglass


Saint Mary's Church

Project/Contract:
Refurbishment

Description: Stripping out of existing roof timbers to expose extent of repairs required for next phase.

Construction Period: 4 Weeks

Status: Completed on time and budget

Architect: Donnelly O'Neill Architects, The Old Throne Hospital, 244 Whitewell Road, Newtownabbey, Co. Antrim BT36 7ES



Client: Belfast Sub Aqua Club


Belfast Sub Aqua Club

Project/Contract:
New Clubhouse For BSAC 030

Description: New build clubhouse including; trenchfill foundations, structural steel, precast floors, red brick external elevation, blockwork internal walls, mechanical and electrical works, rollershutters, aluminium windows, fit out and landscaping.

Value: £240,000.00

Construction Period: 20 Weeks

Status: completed December 2008 ahead programme and under budget

Architect: Gerry O'Connor, 20 Osbourne Park, Belfast


Client: Lisburn YMCA


Lisburn YMCA

Project/Contract:
Refurbishment & Alterations to Lisburn YMCA

Description: Alterations and Refurbishment Works to include; new roof structure and covering whilst building is occupied, new suspended ceilings, upgrade electrics, new toilets including IPS panels, vanity units, flooring, decorations and signage.

Value: £130,000.00

Construction Period: 8 Weeks

Status: Completed Early

Architect: Hall Black Douglas, 152 Albertbridge Road, Belfast, BT5 4GS

Reference:

To Whom It May Concern:

During the months of June & July this year, Bavan Contracts carried out a major contract in Lisburn YMCA, replacing the roof and carrying out major repairs. Now that the work has been completed, I am very satisfied with the improvements undertaken, the standard of workmanship, the management of the same work and the quality of the supervision.

The company worked very closely with the YMCA during the time of the project and was sensitive to the routines of YMCA life. Health and safety issues were always paramount and addressed sensibly by the contractors with risk assessment an integral part of the project. I would be very happy in re-employing Bavan Contracts to undertake any future work at Lisburn YMCA.

Claire Hanna

General Secretary


Client: St John's Ambulance, Saintfield Road, Belfast




Project/Contract:
New extension and general refurbishment of existing buildings including extensive siteworks/drainage

Description: Extension / General fit out works to include; new library, and training rooms. Steel framed structure with kalzip curved roof and full turn key internal finish to high specification including all mechanical and electrical works. Drainage and siteworks incl DDA works.

Value: £175,000.00

Construction Period: 16 Weeks

Status: On Site May 2009

Architect: Blamphin & Associates, 80 Malone Avenue, Belfast. Contact: Paul Blamphin Tel: 9066 7918


Client: Stepping Stones




Project/Contract:
Refurbishment of Skainos Stepping Stones

Description: This scheme relates to the refurbishment of the ground, first and second floors of 240 Newtownards Road, Belfast. Works include; demolition, new services, kitchen, new windows, joinery works, screens, floor finishes and decoration.

Value: £120,000.00

Construction Period: 8 Weeks

Status: Completed

Architect: Donnelly O'Neill Ltd.The Old Throne Hospital, 244 Whitewell Road, Belfast, BT36 7ES. Contact: Paul McMahon T/N: 9077 2244


Client: South Eastern Education & Library Board, Grahamsbridge Road, Dundonald, Belfast (Phase 1)




Project/Contract:
New sports pitch and associated siteworks

Description: New sports pitch, extensive siteworks, drainage, fencing, services, besopke furniture, playground in live school environment

Value: £250,000.00

Construction Period: 12 Weeks

Status: Completed

Architect: Paul Hogarth, Avalon House, 278/280 Newtownards Road, Belfast, Tel - 9073 6690, Contact - Eleanor Lloyd


Client: King & Gowdy Solicitors




Project/Contract:
New Extension & Alterations to Existing Offices

Description: Extension and Refurbishment Works to include;New 3 storey steel framed, ISRC framed building incl all cladding, services, finishes etc. Internal refurbishment to existing offices. Site works to include reinforced retaining walls and ramps, carpark, pallisade fencing etc

Value: £525,000.00

Construction Period: 52 Weeks

Status: Completed January 2010

Architect: Knox & Markwell, 14 Donaghadee Road, Bangor, BT20 5RU. Contact: Clyde Markwell, T/N: 9127 6677



Client: Drumgath GAC


Drumgath GAC

Project/Contract:
Pavilion and Siteworks

Description: New 2 storey steel framed building incl all cladding, services, finishes etc Internal refurbishment to existing clubhouse. Site works to include reinforced retaining walls and ramps, carpark, pallisade fencing etc

Value: £350,000.00

Construction Period: 20 Weeks

Status: Completed May 2010

Architect: Martin Bailie, 19 Newry Street, Rathfriland, Co Down. T/N: 4063 1766


Client: Dunmurry Dental Practice




Project/Contract:
New Extension & Alterations to Existing Offices

Description: Extension and Refurbishment Works to include;Phased operations to semi detached property to create new open planned dental practice whilst still live. Works include extensive refurbishment and extensions to both properties including complete new services to everywhere and new drainage and siteworks.

Value: £425,000

Construction Period: 30 Weeks

Status: Completed July 2010

Architect: Knox & Markwell, 14 Donaghadee Road, Bangor, BT20 5RU. Contact: Neil Morrison, T/N: 9127 6677



Client: Newhill Youth Centre, Whiterock Road, Belfast


Newhill Youth Centre, Whiterock Road, Belfast

Project/Contract:
General refurbishment of existing community buildings

Description: General refurbishment whilst building still occupied to include extensive alterations/demolitions to form new technology rooms, offices and new toilets. New roof lights and extensiverepairs to existing. Upgrade heating system and electrics, new windows and doors, plastering, structural repairs, new floor to sports hall, floor/wall/ceilins finishes throughout, external works/drainage and new fencing.

Value: £150,000

Construction Period: 16 Weeks

Status: Completed April 2010

Architect: Paddy Byrne Architects, Twin Spires Centre, 155 Northumberland Street, Belfast, BT13 2JF. T/N 02890241602


Client: South Eastern Education & Library Board, Grahamsbridge Road, Dundonald, Belfast (Phase 2)


South Eastern Education & Library Board, Grahamsbridge Road, Dundonald, Belfast

Project/Contract:
New Car Park / Childrens Playgrounds

Description: New car park, extensive siteworks, floodlighting, drainage, fencing, services, besopke furniture, childrens playgrounds in live school environment.

Value: £250,000

Construction Period: 16 Weeks

Status: Completed May 2010

Architect: Paul Hogarth, Avalon House, 278/280 Newtownards Road, Belfast. Tel - 9073 6690, Contact - Eleanor Lloyd.


Client: East Belfast Mission




Project/Contract:
Refurbishment of Skyline Building to new cafe

Description: This scheme relates to the refurbishment of old showroom to new cafe including all demolitions/alterations, new wall/floor/ceiling finishes, extensive upgrade of services to meet requirements and new industrial kitchen complete with fit out to cafe.

Value: £150,000

Construction Period: 8 Weeks

Status: Completed June 2010

Architect: Donnelly O'Neill Ltd. The Old Throne Hospital, 244 Whitewell Road, Belfast, BT36 7ES. Contact: Nial O Neill, T/N: 9077 2244


Client: Tullymore Community Centre


Tullymore Community Centre

Project/Contract:
Internal Refurbishment to existing premises

Description: General refurbishment whilst building still occupied to include extensive alterations/demolitions to form new technology rooms, offices and new toilets. New roof lights and passenger lift. Upgrade heating system and electrics, new windows and doors, plastering, structural repairs, new floor to sports hall, floor/wall/ceiling finishes throughout etc

Value: £250,000

Construction Period: 20 Weeks

Status: Completed April 2010

Architect: BGA Architects Ltd, 50 Regent Street, Newtownards, Co.Down. Contact - Mark McCullough, Tel - 91815736


 

Contact Us

Website Designed by Congress
Maintained by Paul McLaughlin

Email